Most component quotes start with last year’s rate and a margin. That works until copper, brass or steel moves, or until a part turns out to need more rework than expected. Here’s a simple structure for the real cost of a part.
1. Material, including scrap
Use the gross weight you actually consume, not the finished weight. For sheet metal, that means the nested sheet area per part. For turned parts, it’s the bar length including cut-off and facing. Price it at today’s rate.
2. Operations
For each operation, take the machine hour rate multiplied by the cycle time, plus setup time divided by batch size. Small batches carry a lot of setup cost.
3. Job work
Plating, heat treatment and coating charges per piece or per kilo, plus transport and any losses beyond the agreed allowance.
4. Overhead
Power, supervision, rent and admin spread across production. Keep the method simple and consistent.
5. Rejection and rework
If 3% of parts are rejected, every good part carries the cost of those rejects. Add rework time as well. This is the line most quotes leave out.